Coastal and flood protection scheme soon to get underway off Lincolnshire coast
Preparations have begun for the continuation of a multi-million pound project to reduce the risk of tidal flooding and maintain beaches on the Lincolnshire coast on the east coast of the UK.
The Environment Agency has set up the compound for its Lincshore beach re-nourishment project. Lincshore aims to combat the decrease in sand levels and increased risk of flooding caused by coastal erosion.
Dredging for Lincshore 2010 will begin in the middle of July and is expected to finish at the end of September. It will see 400,000 cubic metres of sand pumped onto 20km of beach, including Trusthorpe, Boygrift, Trunch Lane, Chapel Six Marshes and Moggs Eye, at a cost of £6 million. (more…)

More than 360,000 cubic metres of sand will be added to a beach on the Norfolk Coast as part of an £8.8m project to prevent the Broads from flooding.